Ireland has binding legal obligations under EU Directive 2009/28 EC to ensure that 16% of all energy consumed in Ireland across the electricity, heat and transport sectors is from renewable sources by 2020. The National Renewable Energy Action Plan sets out that the 16% overall will be achieved by around 40% of electricity consumed being from renewable sources, 12% of consumption in the heat sector and 10% consumption in the transport sector. The first report on the NREAP (submitted in January 2012) is also now available.

REFIT stands for 'Renewable Energy Feed in Tariff' and is the primary means through which electricity from renewable sources is supported in Ireland. The first REFIT scheme ('REFIT 1') was announced in 2006 and state aid approval was obtained in September 2007.

The REFIT 1 scheme was open for applications until 31/12/09 and since that date no new applications have been accepted, although projects accepted into the scheme before that date, which under the relevant legislation were granted an extension of time to become operational, continue to be developed.

There is 1380MW of REFIT  renewable generation capacity supported in the 2012/2013 PSO decision: 55MW of REFIT 2 projects, 2MW of REFIT 3 projects, with the remainder in REFIT 1.

The REFIT 2 scheme (onshore wind, small hydro and landfill gas) was opened in March 2012 and the REFIT 3 (biomass technologies) scheme opened in February 2012. Both schemes are for projects built and operational between 1/1/10 and 31/12/15. See the first question and answer below at REFIT clarifications and Frequently Asked Questions (2011) for further information.


Amendments to the REFIT Terms & Conditions. See here

REFIT 3 (Biomass Technologies)
A number of amendments have been made to the REFIT 3 Terms and Conditions as of August 2012 to clarify the position on a number of aspects of the scheme. The main Terms and Conditions document has been udpated and this REFIT 3 change document sets out what amendments have been made.

REFIT 2 (Onshore wind, hydro and biomass landfill gas)
A number of amendments have been made to the  REFIT 2 Terms and Conditions as of August 2012 to clarify the position on a number of aspects of the scheme. The main Terms and Conditions document has been udpated and this REFIT 2 change document sets out what amendments have been made. 


Reference Prices

Section 5.2 of the Terms and Conditions of the three REFIT schemes provide for adjustments to reference prices by way of annual indexation.

The resulting reference prices, in euro per megawatt hour, are provided in the following tables.

REFIT 1

Year

Inflator

Large Wind

Small Wind

Hydro

Biomass Landfill Gas

Other Biomass

2005

 

57.000

59.000

72.000

70.000

72.000

2006

1.025

58.425

60.475

73.800

71.750

73.800

2007

1.04

60.762

62.894

76.752

74.620

76.752

2008

1.049

63.739

65.976

80.513

78.276

80.513

2009

1.041

66.353

68.681

83.814

81.485

83.814

2010

1

66.353

68.681

83.814

81.485

83.814

2011

1

66.353

68.681

83.814

81.485

83.814

2012

1.026

68.078

70.467

85.993

83.604

85.993

2013

1.017

69.235

71.664

87.455

85.026

87.455


REFIT 2

Year

Inflator

Large Wind

Small Wind

Hydro

Biomass Landfill Gas

2010

 

66.353

68.681

83.814

81.485

2011

1

66.353

68.681

83.814

81.485

2012

1.026

68.078

70.467

85.993

83.604

2013

1.017

69.235

71.664

87.455

85.026


REFIT 3

Year

Inflator

Biomass Combustion

Biomass Combustion - Energy Crops

Large Biomass CHP

Small Biomass CHP

Large AD Non CHP 

Small AD Non CHP

Large AD CHP

Small AD CHP

2010

 

85

95

120

140

100

110

130

150

2011

1

85

95

120

140

100

110

130

150

2012

1.026

87.21

97.47

123.12

143.64

102.6

112.86

133.38

153.9

2013

1.017

88.693

99.127

125.213

146.082

104.344

114.779

135.647

156.516

The balancing payment per megawatt hour in REFIT 1 in 2013 is €10.386, which was increased in line with inflation from €10.212 in 2012.

As set out in the Terms and Conditions of the schemes, the balancing payment in REFIT 2 and REFIT 3 is not subject to CPI and is set at €9.90 per MWh.

REFIT 1 backstop date
In his March 2012 speech to the annual IWEA (Irish Wind Energy Association) conference, Minister Rabbitte noted that he has instructed the Department to seek state aid clearance from DG Competition to extend the backstop date on the REFIT 1 scheme for a two year period up to the end of 2027.

Officials from DCENR are following up on this matter. It should be noted that an extension to the backstop date cannot be confirmed pending the relevant clearance from DG Competition. Any extension to the backstop date is subject to any and all clearances required from the European Commission. 
Update
REFIT 1: Further extensions in time limits to extensions in time already granted in the case of REFIT 1 projects (August 2012)

  1. Projects in REFIT 1 were required to be operational by 31/12/10.
  2. Prior to the introduction of REFIT 2 and REFIT 3, certain projects in REFIT 1 that had not become operational by the required deadline applied for and were granted extensions in time to specified dates, in accordance with sections 7.3 and 7.4 of the REFIT 1 Terms and Conditions.
  3. Some projects that were granted extensions in time to specified dates to become operational have now indicated that they cannot become operational by the date they were granted a time extension to. Some of these projects have sought further extensions in time under REFIT 1.
  4. The Minister has decided that in principle no further extensions in time will be granted under REFIT 1, given that REFIT 2 and REFIT 3 are now up and running.
  5. Due to the short timeframe since the introduction of REFIT 2 and REFIT 3, an exception will be made in the case of extensions in time for projects operational during the upcoming PSO period (1/10/12-30/9/13).
  6. In essence, projects in REFIT 1 seeking further extensions in time to become operational may be granted extensions in time to 30/9/13, but no further extensions will be granted beyond that date.
  7. Project developers that are unable to meet the date they have been granted an extension in time to may apply to transfer projects to REFIT 2 or REFIT 3, where they are in a position to meet the REFIT 2 or REFIT 3 terms and conditions. The application forms for transferring projects can be found in the REFIT 2 and REFIT 3 Terms and Conditions documents above.

REFIT Terms and Conditions, Legislation and related CER Decisions
View terms and conditions for REFIT I (scheme closed for new applications)
2006 clarifications on REFIT 1
January 2009 clarifications on REFIT 1

A number of amendments have been made to the REFIT 1 Terms and Conditions as of August 2012 to clarify the position on a number of aspects of the scheme. The main Terms and Conditions document has been udpated and this REFIT 1 change document sets out what amendments have been made.

European Commission State Aid Decision on REFIT 1 

Section 39 of the 1999 Electricity Regulation Act

SI 217 of 2002
SI 284 of 2008
SI 444 of 2009
SI 532 of 2010
SI 513 of 2011
SI 438 of 2012


PSO Decision 2008/2009
PSO Decision 2009/2010
PSO Decision 2010/2011
PSO Decision 2011/2012
PSO Decision 2012/2013

Certification process for High Efficiency Combined Heat and Power.
CER 08/236 on calculations


REFIT Clarifications and Frequently Asked Questions (2011)

These clarifications are based on a series of representative questions received on the REFIT scheme. These are intended to provide practical advice and should be read and understood in the context of the Terms and Conditions of the REFIT schemes, the applicable legislation, state aid decisions and relevant CER decisions.

Question 1: What are the different REFIT schemes?

Question 2: Will there be an order of merit for processing REFIT 2 and REFIT 3 applications, once state aid approval has been obtained. My project is already operational or nearly operational?

Question 3: Will there be a new REFIT Statutory Instrument published following the introduction of the REFIT 2 and REFIT 3 schemes?

Question 4: How is the CER’s PSO Decision relevant to the REFIT scheme?

Question 5: What is the position on planning permission for REFIT projects?

Question 6: Can I merge two or more projects that are in REFIT?

Question 7: I have a project in REFIT 1 and a project in REFIT 2 on the same site. Can I merge these two projects into one?

Question 8: I am planning to set up as a licensed supplier and it takes CER a certain number of days to process my application. How can I meet the 35 day deadline for submission of a PPA?

Question 9: How are REFIT payments calculated?

Question 10: What is eligible electricity for REFIT payment purposes?

Question 11: Can I use my own meter for metering a REFIT project?

Question 12: Does my REFIT project need to be metered separately? From a technical and market point of view, I am being told it is unnecessary.

Acronyms

Question 1: What are the different REFIT schemes?

Response:

  • REFIT 1” – The original REFIT scheme is now being called REFIT 1 to distinguish it from later schemes. The scheme covered small and large scale onshore wind, biomass landfill gas, other biomass and small hydro (≤ 5MW.)The original REFIT scheme was announced in 2006 and received state aid clearance in 2007. Under the terms of the state aid clearance, no new applications have been accepted since 31/12/2009.
  • REFIT 2” – On 12 January 2012, the European Commission signalled its intention not to raise objections to the REFIT 2 scheme (i.e. state aid clearance to proceed has been received.) In February 2012, the Government approved the introduction of the REFIT 2 scheme.  
  • The Terms and Conditions of the REFIT 2 scheme were published on 21/3/12 and the scheme is now open for applications.
  • The REFIT 2 scheme is intended to cover small and large scale onshore wind, biomass landfill gas and small hydro (≤ 5MW.) To be eligible for REFIT 2, the various requirements that will be set out in the terms and conditions must be fulfilled including proof of planning permission and grid connection -plants must be new plants neither fully commissioned nor operational on 1/1/2010.
  • REFIT 3” –A new REFIT scheme known as REFIT 3 for biomass technologies received state aid clearance from the European Commission in October 2011. Government approval for the REFIT 3 scheme was obtained in December 2011.
  • The Terms and Conditions of the REFIT 3 scheme were published on 27/2/12 and the scheme is now open for applications.
  • REFIT 3 is a scheme to cover 310MW of certain biomass related REFIT categories as follows:
    • 50MW of AD sub technologies (AD CHP ≤500 kW; AD CHP >500 kW; AD (non CHP) ≤500kW; AD (non CHP) >500kW);
    • 100MW of Biomass CHP (non AD) sub technologies (biomass CHP ≤1500kW; Biomass CHP >1500kW);
    • 160MW of biomass combustion and co-firing.
  • The REFIT 2 and REFIT 3 competitions are separate schemes with separate terms and conditons in respect of each scheme.   
  • New clarifications may issue in due course on the new Terms and Conditions, if deemed necessary.
  • Separate state aid applications will be required for any additional new REFIT technology categories that the Government may decide to introduce.

Back to Questions

Question 2: Will there be an order of merit for processing REFIT 2 and REFIT 3 applications, once state aid approval has been obtained. My project is already operational or nearly operational?

Response:

The intention is that the capacity in the new REFIT 2 and REFIT 3 schemes should be largely sufficient in terms of the amount of MW seeking to build and it is not anticipated that the capacity limits for the schemes will be reached in the short term.

It is however expected that once the new schemes are announced, a large volume of applications will be received by DCENR in a very short timeframe with limited resources to process them.

Each REFIT application will be date stamped and logged on receipt (prior to processing), with capacity being tracked in view of any capacity limits.

The processing order for compliant applications will be clarified in the Terms and Conditions of the scheme to facilitate projects meeting the Terms and Conditions that are already operational or that will shortly become operational.

In this regard, it is likely that the application form will require applicants to indicate whether the project is already operational and if not, the expected operational date. DCENR may request further information related to the expected operational date, as they see fit.
Back to Questions

Question 3: Will there be a new REFIT Statutory Instrument published following the introduction of the REFIT 2 and REFIT 3 schemes?

Response:

As explained in response to the following question How is the CER’s PSO Decision relevant to the REFIT scheme?, an updated REFIT statutory instrument is compiled by DCENR on an annual basis to coincide with the commencement of each PSO year (which runs October to September.)

REFIT payments are only made to those suppliers on behalf of specific projects that were notified by the suppliers to be included in the Commission for Energy Regulation (CER)’s PSO Decision, ahead of the commencement of the particular PSO year.

Irrespective of when applications are processed or when the project begins generation, REFIT payments to the licensed supplier in respect of that project can only be made once the specific project has been included in the CER’s PSO Decision. DCENR will therefore continue to update the PSO Order annually in line with the PSO process timelines.
Back to Questions


Question 4: How is the CER’s PSO Decision relevant to the REFIT scheme?

Response:

  • The REFIT scheme is funded through the Public Service Obligation (PSO) charged to all electricity consumers.
  • Section 39 of the Electricity Regulation Act 1999 sets out the legal basis for the PSO.
  • Statutory Instrument No. 217 of 2002 made under Section 39 requires that the Commission for Energy Regulation (‘CER’) calculates and certifies the costs associated with the PSO, including each of the relevant PSO schemes, and sets the associated levy for the required period.
  • The PSO levy takes into account the estimated and actual costs incurred in undertaking generation activities which are covered in the relevant PSO legislation, including costs associated with the REFIT scheme.
  • The PSO levy year runs from 1 October to 30 September.
  • Under the terms of the REFIT scheme, each generator is obliged to enter a PPA with a licensed supplier.
  • In accordance with its PSO timelines, the CER writes to all licensed electricity suppliers requesting the relevant information it requires to calculate the REFIT PSO levy for the upcoming PSO year. [By way of information, CER usually sends these letters around springtime in line with its PSO timelines.]
  • The CER then calculates the amount of the PSO related to REFIT on the basis of the information provided to it by suppliers and other relevant information as outlined in CER's PSO decision papers (available at http://www.cer.ie/
  • Only those projects that have been notified to CER by suppliers and included in the relevant PSO calculation for the PSO levy decision by CER are eligible for REFIT payments in the relevant PSO period.
  • DCENR then verifies that all those projects that are to be paid REFIT in the upcoming PSO year are included in the latest annual REFIT statutory instrument (S.I.)
  • Payments cannot be made unless the project is also listed in the S.I.
  • DCENR updates the REFIT statutory instrument annually in accordance with the PSO process timelines to reflect any changes.
  • It is for the parties to the REFIT PPAs (i.e. the generators and suppliers) to ensure communication with each other on the state of play of projects and to ensure that CER is provided with timely information each year by suppliers in accordance with its PSO timelines. 

Back to Questions 

Question 5: What is the position on planning permission for REFIT projects?

Response:

  • Under the REFIT Terms and Conditions, only projects that can demonstrate valid planning permission will be accepted into the scheme.
  • It is imperative that projects continue to hold valid planning permission until such time as the development has physically taken place in accordance with the planning permission decision.
  • Projects that do not yet physically exist and that are unable to demonstrate proof of valid planning permission are deemed to be non compliant with the REFIT Terms and Conditions and will be removed from the scheme.
  • Where planning permission expires, the onus is on the REFIT applicant to promptly submit further proof of continued planning permission for the development (e.g. proof of an extension in time) to DCENR

Back to Questions

Question 6: Can I merge two or more projects that are in REFIT?

Response:

  • For mergers to take place, a request in writing to merge the projects must be submitted to DCENR.
  • The projects merging must all be part of the same REFIT scheme (i.e. all in REFIT 1 or all in REFIT 2 etc.)
  • The merged project must all be in a single REFIT technology category (e.g. entire project is large wind.)
  • If any of the original projects (proposed for merger) are already in receipt of REFIT payments, then a merger cannot in principle take place. In principle if projects are merged, the entire merged project must have the same start and end date for REFIT payment purposes.
  • The exception to projects requiring the same start date is where one project is already in receipt of REFIT payments and is merged with another new project, and the applicant agrees that the entire merged project will end the date the first project in the merger is due to finish receiving REFIT payments (i.e. that the second project in the merger will not receive the full 15 years of REFIT payments.)
  • Planning permission for the merged site must remain valid. If new planning permission for the merged project is not being submitted, a written declaration from the applicant must be supplied that the merged site will remain fully compliant with the conditions of the individual original planning permissions that were granted for the separate projects.
  • Proof of grid connection for the merged project must be supplied
  • Are the projects under the same ownership? If not, proof of the willingness (to accede to the merger) of the original REFIT applicants must be submitted in writing to DCENR on headed paper.
  • The merged project must be subject to a single REFIT Power Purchase Agreement and be metered as one project.
  • The REFIT statutory instrument may need to be amended in the following annual update by DCENR to reflect the merged site.

Back to Questions

Question 7: I have a project in REFIT 1 and a project in REFIT 2 on the same site. Can I merge these two projects into one?

Response:

  • It is not possible to merge the two projects, if they both remain in different schemes. This is because separate metering for each project would be required in that instance.
  • If neither of the projects is yet in receipt of REFIT payments, then it is possible to merge these into a single project under REFIT 2. The conditions outlined in response to Question 6 would apply in that case.
  • It is not possible to merge the projects into a single project under REFIT 1 as that scheme has closed and no new additional MW can be entered into that scheme.
  • In the event that you wish to merge the two projects under REFIT 2, you should apply for REFIT 2 for the entire project (once DCENR has received state aid clearance and published the scheme) and at the same time notify DCENR that you are forfeiting the MW of the project currently in REFIT 1, provided the entire project is accepted into REFIT 2.
  • The REFIT statutory instrument may need to be amended in the following annual update by DCENR to reflect the merged site.

Back to Questions

Question 8: I am planning to set up as a licensed supplier and it takes CER a certain number of days to process my application. How can I meet the 60 day deadline for submission of a PPA in REFIT 2 and REFIT 3?

Response:

  • Evidence of Power Purchase Agreements (PPAs) will only be accepted in the REFIT scheme as valid if they are with a supplier that has been licensed by the Commission for Energy Regulation (CER)
  • Those accepted into the REFIT scheme must supply evidence of a PPA with a licensed supplier within 60 days of receiving a REFIT letter of offer from DCENR. In the absence of fulfilment of this criteria and evidence of a REFIT PPA being submitted within the timeframe, projects may be removed from the scheme.
  • Where an applicant is in the process of obtaining licensing as a supplier from the CER, the Department will initially accept evidence that a comprehensive application to become a licensed supplier has been submitted to CER, provided that within a further 60 days thereafter, evidence of the PPA is submitted to DCENR.
  • In the absence of a follow-up indicating that the supplier has become licensed and that a PPA is in place, such projects may be removed from the scheme.

Back to Questions

Question 9: How are REFIT payments calculated?

Response:

  • CER 08/236 Decision Paper entitled ‘Calculation of the R-factor in determining the Public Service Obligation Levy’ outlines how REFIT payments are to be calculated in accordance with the REFIT Terms and Conditions.
  • Essentially the calculation is to be carried out on a PSO period basis
  • Total market revenues are compared to entitled REFIT costs to determine REFIT support under the REFIT Terms and Conditions. The total market revenues and total REFIT costs in the calculation are the sum of the respective amounts in each PSO period.  
  • Further detail is set out in sections 4.8 and 4.9 of the Decision Paper CER 08/236. The CER Decision Paper is available above and on the CER website: http://www.cer.ie/

Back to Questions

Question 10: What is eligible electricity for REFIT payment purposes?

Response:

  • Electricity that is eligible for REFIT payments is exported metered generation as set out in Statutory Instrument 532 of 2010 and defined in section 4.2 of CER Decision Paper 08/236.
  • It is emphasised that REFIT is not payable for generation consumed onsite i.e. that is not exported through the commercial point of entry to the Transmission or Distribution system or at the trading boundary.
  • The CER Decision Paper 08/236 entitled ‘Calculation of the R-factor in determining the Public Service Obligation Levy’ outlines how REFIT payments are to be calculated in line with the REFIT Terms and Conditions.
  • The Decision Paper includes definitions of metered generation and metered generation loss factored (to be included in the way the REFIT payments are calculated) at section 4.2.
  • The date from which REFIT support commences in respect of a particular REFIT project, to a maximum of 15 years, is outlined in Statutory Instrument 532 of 2010. It states that ‘The period of the public service obligations to be imposed… commences, in respect of a REFIT power purchase agreement… the date on which the supplier purchases output from the plant of the generator which is exported for the purposes of distribution or transmission.

Back to Questions

Question 11: Can I use my own meter for metering a REFIT project?

Response:

  • It is a requirement of the REFIT scheme that official EirGrid/ESB Networks meters are installed and polled by EirGrid/ESB Networks as appropriate for the purposes of metering REFIT.
  • The meters used by EirGrid/ESB Networks are of a certain approved standard and ensure compliance with the CER Metering Code. Retention of meter data with EirGrid/MRSO facilitates cross-checking, from a PSO Certification perspective and relevant duties.

Back to Questions

Question 12: Does my REFIT project need to be metered separately? From a technical and market point of view, I am being told it is unnecessary.

Response:

  • REFIT projects need to be metered separately. Discrete REFIT project metering to an appropriate standard is a cost of participation in the REFIT scheme.
  • Separate metering of REFIT projects is necessary to ensure that the CER (from a PSO certification perspective) has clarity on what exactly is eligible for REFIT at what rate/amount etc.
  • While there may be no reason from the developer’s perspective to install a separate additional sub-meter on a site from a technical/market/engineering perspective, this is necessary if the project is being accepted into REFIT as a separate REFIT project.
  • If a project eligible for REFIT is built behind an existing single meter that is already in use, an individual meter or sub-meter in respect of that project is required in order for output to be accurately measured for the calculation of PSO payments. An example would be where a REFIT project is operating and metered on a particular site. A new separate second project is built beside it. The second project requires separate metering/sub-metering.
  • There are many reasons why separate metering of REFIT projects is deemed necessary in order to be able to calculate and certify PSO payments accurately.

Back to Questions

Acronyms & Commonly Used Terms

CER – Commission for Energy Regulation

DCENR - Department of Communications, Energy & Natural Resources

EirGrid – the Irish Transmission System Operator

ESB Networks – the Irish Distribution System Operator

MEC – Maximum Export Capacity

MRSO -Meter Registration System Operator

MW - megawatt

PPA / PPAs– Power Purchase Agreement(s)

PSO – Public Service Obligation

REFIT – Renewable Energy Feed in Tariff

SEM – Single Electricity Market

S.I. – Statutory Instrument


List of Licensed Suppliers in REFIT


REFIT and Guarantees of Origin (GOs)

The Renewable Energy Directive (2009/28/EC) provides for Guarantees of Origin (GOs) for renewable generation. GOs, according to the Directive, have the sole function of proving to a final customer that a given share or quantity of energy was produced from renewable sources.

GOs under the Directive are completely separated out from target compliance and cannot be used for renewable trade purposes between countries to meet their target (which can only be done under the co-operation mechanisms in the Directive.)

The provisions on GOs in the Renewable Energy Directive were transposed into Irish legislation by SI 147 of 2011. In November 2011, the Commission for Energy Regulation published CER 11/284 entitled 'Supervisory Framework for the administration of Guarantees of Origin.' Further information on the GO system to apply in Ireland can be found in that document.

SI 147 of 2011, in line with the provisions in Directive 2009/28/EC provides that where a PSO generator receives a GO for a renewable energy unit, no support scheme payment for the same unit of electricity shall be made. A PSO generator means a generator that is party to a current REFIT or AER PPA.

The reasoning behind this Decision which is provided for in the Directive is that the final consumer through the PSO levy fund has already provided support for a certain amount of renewable generation and this should be reflected in the fuel mix disclosure provided to consumers.

Under the relevant CER Decision CER 11/284, in accordance with the Regulations any renewable generator that is covered by REFIT or AER and wishes to remain in receipt of support will not receive a GO. The generator will have the attributes of their generation transferred directly to the fuel mix of the supplier with whom they have their Power Purchase Agreement (PPA) under the support scheme. Neither any generator nor the supplier will be able to transfer the attribute to any other party and it will be applied to the supplier’s fuel mix for the disclosure period in which the generation occurred.

Correspondence between the European Commission and Ireland on REFIT 1 state aid application

Notification Document
Part I Published Terms and Conditions
Part I S39
Part III Supplementary Information on Environmental Protection Aid
Query 1 from EC 27 October 2006
Response from Department 31 January 2007
Query 2 from EC 30 March 2007
Response from Department 23 April 2007
Submission 3 May 2007
Submission 4 July 2007
Submission 13 September 2007
Commission Decision 25 September 2007
Request for Access to Documents from EC 25 September 2008

Additional REFIT categories
Separate state aid applications and state aid clearance will be required for any additional REFIT technology categories, prior to the introduction of corresponding new REFIT schemes.


 