Menu

Letter from Tom Reeves

PDF version 92kb

23rd December 2004

Mr Noel Dempsey, TD Our Ref: 19709

Minister for Communications,

Marine and Natural Resources

Adelaide Road

Dublin 2

RE: Interim Renewable Support Mechanism to achieve 2010 target

Dear Minister,

Prior to the taking of a final decision by you on the matter of the proposal for an

interim renewable support mechanism to achieve the RES-E Directive target of

13.2% of consumption from renewables by 2010, I wish to take the opportunity

to re-iterate the Commissions views as expressed in previous discussions with

your Department and the Renewable Energy Development Group (REDG).

First of all let me emphasise that we are committed to working towards the

RES-E Directive target for renewables and we firmly believe that the target will

be achieved prior to 2010. However, in line with our duty under the Electricity

Regulation Act, 1999 to minimise the cost to consumers and to promote

competition the target should be achieved in a manner that delivers best value

to the final customer.

Having concluded that the implementation of a renewable obligation and

tradable certificate scheme is not practicable in the short-term, the options

remaining are i) build on a merchant basis, ii) a competitive tender system or iii)

a fixed feed-in tariff.

The Commission is strongly in favour of option i) and remains unconvinced of

the need for additional support at this time. We are aware of significant

appetite in the market for merchant plant in particular for the more mature

renewable technologies i.e. onshore wind. Of the 233MW of wind currently on

the system 83MW (36%) has been built on a merchant basis and at least a

further 82MW is under construction. There is, therefore, a track record to show

that plant can be built on a merchant basis. In addition the large number of

projects (2,494MW) in the applications process for connections from the

network operators illustrates clearly that there is no need to further stimulate

the sector at this time.

Recent representations to us by an independent supplier in the market should

also be noted here. This supplier had reached agreement with a number of

developers and their bankers on long-term contracts only for the developers to

avail of an opt-out clause in the contracts when it became clear last week that

they would be offered AER contracts with preferential terms under the Reserve

List. Independent suppliers cannot hope to compete with AER contracts as

evidenced above. However, bilateral contracts with no Government support

element (and as such no impact on the PSO) represent better value for the

customer and help to promote competition.

Bearing in mind the Commissions position as outlined above, should you take

the decision to implement an interim support mechanism we believe that:

" the mechanism should be implemented in a manner that does not act to

deter merchant build;

" a competitive tender support system would deliver the target at a

relatively lower cost to the consumer than a fixed feed-in-tariff due to the

inherent competitive bidding process;

" the mechanism should be accessible to independent suppliers in the

market not just to PES;

" less mature technologies should be supported through secondary

support mechanisms, for example, capital grants, and as such not

funded through the PSO;

" a fixed-feed-in-tariff system should not be pursued unless the level of the

support is set at a considerable discount on the existing AER VI reserve

price.

Finally, the Commission notes that support funded through the PSO is costly

for the consumer (for example, adding €20million to the PSO will mean a 1%

increase in the retail tariff on average). In addition, increases in the PSO have a

negative impact on competition as they erode the margin for independent

suppliers to compete on. It also needs to be taken into account that the Best

New Entrant (BNE) price (above which costs are passed through the PSO) is at

an all-time high. It is uncertain whether this figure will remain at its present

level. In addition, with the commencement of a new trading system in 2007 the

average market price will be used as the benchmark figure and this is likely to

be lower than the present BNE thus further increasing the PSO.

I trust that you will take account of the Commissions views when reaching a

decision on this matter. The benefits of wind as a fuel saver are well known but

the impact and cost of large amounts of wind on the system are not. Clarity on

this is required and we look forward to the re-commencement of the REDG in

2005 and the examination of the full costs and benefits of increased penetration

of wind generation on the system. We see this work as a priority so as to inform

policy regarding renewables and the setting of targets post 2010.

Yours sincerely,

Tom Reeves

Chairman

Department of Communications, Energy and Natural Resources29-31 Adelaide Road, Dublin 2, Ireland
Tel +353-1-6782000 Fax +353-1-6782449