MANs Phase I

 

Consists of 27 towns covering 11 Authority regions . Handover to the Management Service Entity(MSE) E-net has now been completed for 27 of these towns .

 

The following are a list of towns the are part of Phase I MANs


 
Town  
Start Date Handover KM
Athlone May-03 15/12/2004 20.50km
Ballina April 03 4/10/2004 19.90km
Carlow Nov-03 20/04/2005 13.50km
Cavan Jan-05 17/01/2006 13.90km
Carrick-on-shannon Aug-03 14/06/2005 10.00km
Carrickmacross Jan 2005 28/02/ 2006 4.90Km
Clonmel Nov-03 15/12/2005 19.30km
Cork Apr-03 06/04/2005 58.70km
Drogheda Jan-05 28/02/2006 17.75km
Dundalk Jan-05 28/02/2006 17.70km
Dungarvan Nov-03 15/12/2005 9.50km
Galway Feb-03 27/09/2004 51.70km
Gweedore Aug-03 23/05/2005 4.50km
Kilkenny Nov-03 20/04/2005 15.26km
Kiltimagh April-03 04/10/04 3.50km
Kingscourt Jan-05 17/01/2006 4.50km
Letterkenny Oct-03 15/12/2004 19.50km
Limerick Nov-03 06/10/2005 63.00km
Monaghan Jan-05 08/02/2006 18.50Km
Manorhamilton Aug-03 14/06/2005 5.10km
Mullingar May-03 25/01/2005 20.90km
Portlaoise May-03 25/01/2005 15.25km
Roscommon May-03 25/11/2004 12.20km
Sligo Oct-04 24/11/2005 24.00km
Tullamore May-03 25/01/2005 14.55km
Waterford Nov-03 28/02/2005 20.36km
Wexford Nov-03 14/06/2005 28.70km


Start = Commencement of construction

Handover = Date taken in charge by e-Net